We are now in the final phase of the maternity ward construction. The contractor has assured me that the building will be completed and have an occupational certificate by the end of October. This will enable the official opening to … Read More

April 2022

At last it looks like the Rwandan Government are about to finish the new road to the hospital, they have built the retaining wall and replaced the access from the mission to the hospital. Building work continues on the Maternity … Read More

March 2022

Phase 2 is almost complete. The walls are finished, steel roof support are in place and work has begun on the roof. We expect to begin the third and final phase of construction in April and should be completed by … Read More

Aug 21 – Maternity

All the necessary building permits are now received, a contract has been signed with a building contractor and work has started. Foundations are being dug for the supporting wall and modifications made to the old maternity to make room for … Read More